Pneumatic butterfly valves are commonly installed in heating, gas, and water supply pipelines. In thermal power systems, triple-offset metal-seated butterfly valves are generally preferred. After installing butterfly valves and pipelines, purging is required. The three commonly used purging methods are water flushing, air purging, and steam purging. The specific requirements for each method are as follows:



Water Flushing


1.Clean water must be used for flushing pipelines. When flushing austenitic stainless steel pipelines, the chloride ion content in the water must not exceed 25×10⁻⁶ (25 ppm).


2.Flushing should be conducted at maximum flow rate, with the flow velocity not less than 1.5 m/s.


3.The discharged water should be directed to a reliable drainage pit or channel. The cross-sectional area of the drainage pipe must not be less than 60% of the cross-sectional area of the flushed pipe. Negative pressure during drainage is not allowed.


4.All drainage branches of the pipeline must be thoroughly flushed.


5.Flushing should be continuous, and the process is considered complete when the water at the outlet matches the inlet water in color and clarity upon visual inspection.


6.If the pipeline is not immediately operational after flushing, it should be completely drained and promptly dried.



Air Purging


1.Air purging should utilize a large compressor from the production facility or large storage vessels for intermittent purging. The purging pressure must not exceed the design pressure of the vessel and pipeline, and the flow velocity should not be less than 20 m/s.


2.When purging oil pipelines, the air must not contain oil.


3.During air purging, once the exhaust is visually free of smoke or dust, a wooden target board covered with white cloth or painted white should be placed at the exhaust outlet for inspection. The purging is deemed complete if no rust, dust, moisture, or other debris appears on the target board within 5 minutes.



Steam Purging


1.Temporary piping for steam purging must be installed in accordance with the technical requirements for steam pipelines, and the installation quality must comply with the relevant standards.


2.Steam purging should be performed with high-flow steam, with a flow velocity of no less than 30 m/s.


3.Before steam purging, the pipeline should be preheated, water should be drained promptly, and thermal displacement of the pipeline should be checked.


4.Steam purging should follow a heating–cooling–reheating cycle, purging one pipeline at a time in a sequential manner.


5.Steam pipelines leading to turbines or as specified in design documents must have their target plates inspected after purging. If no specific requirements are stated, the purging quality must meet the relevant standards.